ONE of OURE WORKS

AUTBA BIN GAZWAN PAVEMENT

Project title:Autba Bib Gazwan road renovation

Beneficiary side:Baghdad municipality

Contract no.81 /2008

Location:Baghdad-AL-Dora

Contract amount:5,962,450,000 ID

Contract period:160 days

Description

Demolish and remove the old bad sectors of the pavement and

replace it with new two layers ( stabilizer 5 cm and surface 5 cm ) also

renovation of the middle rain channel , install guard rail type B 5 km

length , the work was completed according to specifications and with

in contract time