ONE of OURE WORKS

FALLUJAH ELEVATED TANK RENOVATION

Project title:Fallujah south water elevated tank renovation

Beneficiary side:Fallujah rehabilitation committee

Contract no.W917BG-05-C-0036

Location:South of Fallujah in nezal district

Contract amount:69,000$

Contract period:3/2/2005-3/4/2005

Description

when the project was awarded the elevated tank was damaged by bolts so the construction committee of Fallujah decided to fix all the halls in the body of the tank and finishing them properly with good quality painting and we put tow engineers to look after this project because it is very important for Fallujah city , there was tow committees inspect our project one from the USACE and the other from Iraqi government , when the work was completed we test the elevated tank to see if it is workable or not and the result was very positive so we deliver the tank to the Iraqi government and the water arrived to each single house in that area, the work was include fixing the halls and cracks ,painting and testing